Sheetrock


It’s finish time. They say production builders can go from drywall to final inspection in 45 days. With drywall completion yesterday June 5th, that would be about July 20th. I’m pretty certain it will take me quite a bit longer to get there, but with a little luck, I’ll be done in early-mid August or so. Here’s a picture I took in the kitchen looking out into the living/dining areas. Not much to see, the windows and doors all taped over so very little light in here.